NDOT 3270 US 95 SEARCHLIGHT

NDOT 3270 US 95 SEARCHLIGHT

670 U.S. 95
Searchlight, NV 89046

Type of Job:  22 miles of highway reconstruction taking a two lane arterial road and making a four lane divided highway.
Cost:  $48 Million
Duration:  2008
Location:  US 95 from Searchlight to the Arizona state line south of Las Vegas
Project Status:  Complete
Client:  NDOT
Sterling Company:  Road & Highway Builders

The project was a fast track contract mandating six days per week and 24 hour per day operations.  The project required 40 trucks, double shifted, operating out of two aggregate gravel pits.  At the height of production, RHB was importing over 40,000 tons per day to construct the new highway alignment. The project required over 2 million tons of import that included 330,000 tons of asphalt paving.  The project was completed ahead of the 200 day schedule.